While Trump continues to play his fruitless, change-by-the-hour activities with Iran, he is failing to maintain the combat readiness of U.S. Navy submarines.
Since “the U.S. Navy’s attack submarines gather intelligence undetected and attack enemy targets,” the declining maintenance of such essential hardware is quite a concern, according to a recently-released report on the matter from the Government Accountability Office (GAO).
“Ten years of maintenance delays for these submarines have resulted in over 15,000 lost operational days and an estimated $3.4 billion in costs” to U.S. taxpayers, continued the study.
Below, The American Spark quotes the introductory “Fast Facts” and “Highlights” sections of the GAO report.
Note: Under the “Highlights” portion of our reprint, The Spark has placed the section entitled, Why GAO Did This Study ahead of the section entitled, What GAO Found, to enhance clarity and readability.
Fast Facts
“The U.S. Navy’s attack submarines gather intelligence undetected and attack enemy targets. 10 years of maintenance delays for these submarines have resulted in over 15,000 lost operational days and an estimated $3.4 billion in costs.
“Additional delays are on the rise as submarines wait to be decommissioned—taken out of service—because shipyards don’t have the capacity to start that process. With more submarines needing to be decommissioned in the next 5 years, decommissioning delays could cost the Navy more than $3.1 billion.
“Finding alternative ways to reduce backlogs could save the Navy billions of dollars.
“Our recommendations address this.”
Highlights
Why GAO Did This Study
“According to the U.S. Navy, its 44 attack submarines, as of fiscal year 2025, provide the United States an asymmetric advantage to gather intelligence undetected and attack enemy targets, among other missions. These capabilities make attack submarines some of the most requested assets by the global combatant commanders.
“House Report 118-529 includes a provision for GAO to assess the readiness and availability of the U.S. Navy’s attack submarine fleet. This report discusses the extent to which the Navy has effectively maintained its attack submarine fleet and has mitigated any challenges. GAO analyzed U.S. Navy attack submarine maintenance data from fiscal years 2016 through 2025, reviewed U.S. Navy documentation, and interviewed officials.
“This report is a public version of a classified report GAO issued July 16, 2026. GAO omitted information the Department of Defense deemed classified or sensitive, such as attack submarine operational availability and how the U.S. Navy’s approach to attack submarine force generation compares to strategic competitors’ approaches.”
What GAO Found
“The U.S. Navy has not fully mitigated attack submarine fleet maintenance and other challenges affecting readiness. Over the last 10 years, the U.S. Navy has lost more than 15,000 operational days due to maintenance delays and idle time on active attack submarines. These delays resulted in an estimated $3.4 billion in costs to sustain crews and submarines that provided no operational capability.
“Lost operational days include delays completing depot maintenance and active idle time. Active idle time describes a period when an attack submarine and its crew must remain pier-side because they are no longer certified to conduct normal operations and cannot be inducted into a maintenance period. In addition to lost operational days, the Navy faces significant challenges with managing inactive idle time for attack submarines. Inactive idle time describes when an attack submarine designated for decommissioning cannot be inducted into a dry dock in a shipyard. As a result, the submarine and its crew must remain pier-side until a shipyard has the capacity in a dry dock to defuel their nuclear reactor.
“While the U.S. Navy has made recent progress in reducing active idle time, inactive idle time for submarines has grown and is projected to worsen. Without mitigation, 15 attack submarines will enter inactive idle time from fiscal year 2026 through fiscal year 2030—during which time the Navy could incur more than 14,000 days of inactive idle time and $3.1 billion in costs to operate and support these inactive submarines. The U.S. Navy has not fully evaluated alternative options to more efficiently decommission attack submarines and develop and implement an inactivation plan that could allow them to reduce inactive idle time for crews and save billions.”
Recommendations
“GAO is making two recommendations including that the U.S. Navy fully evaluate alternative options to more efficiently decommission attack submarines and develop an attack submarine inactivation plan that reduces inactive idle time. The Navy verbally concurred with GAO’s recommendations, but did not provide written comments.”